Chilean Operational Plan

Laguna Verde - Year 1

  • Sampling and volumetric calculations of contained light metals in surface lake waters (completed)
  • Inferred resource estimate (completed April 2010)
  • Filed backup technical reports that support the inferred resources estimate (completed June 2010)
  • Tenders for brine chemistry process design, scoping study (July 2010)
  • Select and engage consulting / engineering firm for scoping study (August 2010)
  • Commence scoping study (3-4 months anticipated)
  • Update resource calculation through scoping study and additional analysis to indicated or measured resource category
  • Select and engage consulting / engineering firm for pre-feasibility study

Laguna Verde - Year 2

  • Complete pre-feasibility study
  • Tenders for feasibility study for surface water exploitation facilities - target 10,000 tpy of LiCO3
  • Design/engineering of facilities to recover light metals from surface waters
  • Commence permitting of facilities for production from surface lake(1)
  • Begin exploration program for deeper brines

Laguna Verde - Years 3 & 4

  • Complete construction of and commercial production at surface water facility
  • Complete scoping and pre-feasibility studies for deeper brines
  • Begin feasibility and conceptual engineering based on the deeper resource base
  • Commence permitting and construction process for full scale deep brine operation
  • Design, construct, and commission deep brine recovery plant
  • Commence operations from deeper brines

 Laguna Brava and Rio de la Sal

  • Exploration programs planned followed by a similar strategy as above

(1) Subject to completion of satisfactory feasibility study and contingent on adequate financing